Experience
> Solid & Hazardous Waste Projects
|
<< Return
|
Solid & Hazardous Waste Projects
|
 | | | Pecan Grove Landfill Cell 16 | Waste Management of Mississippi
Pass Christian, Mississippi
Beard Construction Group was awarded the contract to construct a 15 acre solid waste landfill for Waste Management in Pass Christian, Mississippi. | | Timberlands Landfill MSW Cell Construction | BFI/Republic Services
Brewton, Alabama
BCG was awarded a contract to construct a 5 acre landfill cell for BFI/Republic Services’ Timberlands Landfill in Brewton, AL. | | Pecan Grove Sanitary Landfill | Waste Management, Inc.
Pass Christian, Mississippi
Beard Construction Group was awarded the $1.8 million contract to construct an 11.5 acre landfill cell for Waste Management of Mississippi. | | Phase 4 Cell Construction |
BFI Waste Systems
Kiln, Mississippi
Beard Construction Group was awarded the contract to construct a 9 acre solid waste landfill for Hancock County Development Company in Kiln, Mississippi. | | Timberlands Landfill Cap Construction | BFI/Republic Services
Brewton, Alabama
A project team was assembled in the bid phase of the project, which consisted of a national engineering firm, HDR Engineering, Beard Construction Group and another local construction firm. The team was awarded the project based on a competitive and innovative proposal, which offered the customer the "best overall value”. | | Landfill Cell & Clay Cap Construction | BFI Waste Systems
Welsh, Louisiana
Beard Construction Group was awarded a contract to construct an 8.8 acre landfill cell and close an existing cell that has reached a certain height and capacity. |
|
|
|
|