Gas Storage Project - Brine Pond Construction

URS Energy & Construction, Inc.
Franklin Parish, Louisiana
 
Beard was awarded the contract to construct a 30 acre site consisting of three brine pond storage facility to support an underground gas storage cavern. The brine ponds included primary east pond, a primary west pond and a secondary pond all lined with a conductive HDPE liner for leak detection. The facility will be adding a compressor station and for the storage and transport of natural gas.
 
   
Scope of Work
  • Erosion and sedimentation control—silt fence, berms and grading and hay placement
  • Clearing, grubbing the 30 acre site
  • Removal of 31,468 CY of topsoil
  • Installation of 964 LF of 12” RCP an 18” carbon steel pipe with HDPE casings
  • 3,090 lf of French under-drain system
  • Installation of 457,536 SF of conductive HDPE liner & leak detection system.
  • Installation of shoring & dewatering systems
  • Installation of sumps, pipe, culverts & manholes
  • Ditches, roads, parking with sub-base compaction, filter fabric and stone surfacing
  • 168,418 CY of mass earthwork for the cut & fill of the three brine ponds
  • Seeding, hydro-mulching, re-vegetation of 12.7 acres
Beard Contract Value: $ 2.5 Million
Project Start Date: June 2010
Completion Date: September 2010
 
 

 