Gas Storage Project - 40 Acre Site Work
|
URS Energy & Construction, Inc.
Franklin Parish, Louisiana
In addition to a 30 acre site work contract to construct brine ponds, Beard was awarded the contract to construct an additional 40 acre site which will support the administrative and operations building, a pipeline interconnection, a compressor station and two underground commercial storage cavern for storing natural gas. This was a FERC approved facility.
 |
|
 |
|
|
|
|
The Scope of Work Included:
- Clearing and grubbing
-
Removal of 155,832 CY of topsoil.
-
139,640 CY of structural fill
-
2,024 LF RCP 12” - 30” diameter pipe
-
78 Tons of rip rap
-
13,242 SY sub-base compaction for roads and parking
-
13,833 SY of filter fabric for crushed stone surfacing
-
2,352 SY concrete paving
-
Installation of catch basins, 36 X 36 slide gates with anchors
-
Mass earthwork for lay-down, parking and temporary facilities
-
Finish grading
-
139,646 SY topsoil replacement
-
Seeding and mulching 31 Acres
-
92,302 CY of mass earthwork for lay-down, parking and temporary facilities
Beard Contract Value: $ 1.83 Million
Project Start Date: June 2010
Completion Date: September 2010 |
|
 |
| |
|
|
|
|