Activated Carbon Plant

ADA-Carbon Solutions
Coushatta, Louisiana
 
Beard was awarded the $5.6 million contract to develop the twenty acre site of ADA's first Activated arbon production facility. Beard was awarded an additional $2.4 Million contract for the installation of fire water and storm sewer piping.
 
Scope of Work
  • 200,000 CY of excavation
  • 200,000 CY of imported select fill
  • 40,000 tons of crushed stone
  • 248 LFof 84” PCP pipe
  • 53,000 SY of geo-grid
  • Storm-drainage system
  • Fire-water piping
Beard Contract Value: $ 8 Million
Project Start Date: September 2008
Completion Date: September 2009
 
 

 