Joint Force Headquarters
|
|
Walton Construction
Pineville, Louisiana
Walton Construction, general contractor, was awarded the contract for the Joint Force Headquarters at Camp Beauregard. The contract value totaled approximately $30 million. Walton Construction awarded Beard Construction Group the civil construction phase which included the site work, drainage, parking lots, access roads, building pad and concrete foundations. Over 98% of the work was performed by Beard’s own forces.
 |
|
 |
|
|
|
|
|
|
Construction Activities Included:
-
Demolition of Buildings
-
55,000 CY of Excavation & Embankment
-
12,000 CY of Crushed Stone Placement
-
16,000 SY of Concrete Paving
-
1,600 CY Concrete Foundations
-
3,000 LF of Reinforced Concrete Pipe (RCP)
-
60 Storm Drainage Boxes
-
92 Drill Shafts
Beard Contract Value: $ 6.2 Million
Project Start Date: February 2007
Completion Date: September 2008 |
| |
|
|
|
|