Aviation Maintenance Hangar

Walton Construction
Fort Polk, Louisiana
 
The project scope includes all phases of site development for the Aviation Maintenance Hangar and the UAV Shelter at the Fort Polk military base in Alexandria, LA. The new facility covers a 40 acre site.
Construction Activities Included:
  • 1,200 CY of Asphalt Demolition
  • 3,654 CY of Concrete Demolition
  • Piping Demolition
  • 12 Acres of Clearing & Grubbing
  • 29,040 CY of Stripping
  • 782,000 CY of Earthwork
    • Stripping
    • Excavation
    • Embankment
  • Storm Drainage
    • 1,520 LF of Box Culverts
    • 17 12" - 36" Headwalls
    • 5,685 LF of 12 - 36" Storm Drainage Pipe
    • 32 Storm Drain Inlets
    • 10 Storm Drain Inlets
    • 7 Manholes
  • Erosion Control
  • Retention Pond
  • Sedimentation Pond
  • 15,800 CY Crushed Stone
  • Surface Rock for Access Roads
  • 95,150 SY Lime Stabilization
  • 6,900 CY of Rip Rap
  • 5,100 Tons of Asphalt Paving
  • 15,500 Tons of Asphalt Drainage Layer
Beard Contract Value: $ 7.2 Million
Project Start Date: October 2004
Completion Date: August 2006
 
 
 
 

 