Project Experience
Experience > Transportation Projects > Site Rail Installation Phase II

<< Return

Site Rail Installation Phase II

Shintech Louisiana, LLC
Plaquemine, Louisiana
Beard was awarded the $3.96 Million contract for the Site-Work and Concrete portion of the second phase of Shintech's Rail Expansion project at their Plaquemine Plant in Iberville Parish, Louisiana. Beard's scope of work included the site preparation to install 55,000 track feet for a new rail spur and expansion, rail storage facility, weigh-in-motion scale and scale house.
 
Construction Activities Included: 
  • 25-Acres clearing & grubbing
  • 35,000 CY stripping
  • 30,000 CY excavation
  • 10,000 CY embankment
  • 135,000 SY lime stabilization
  • 60,000 Tons ballast stone
  • 60,000 Tons sub-ballast stone
  • Storm Drainage
  • 1,000 LF 12” - 36” HDPE
  • 500 LF 12” - 54” BCCMP
  • Headwall/Containment structure
  • 23,000 SY permanent geocomposite
  • 18,000 LF 8” PVC underdrain system
  • 10,000 Tons limestone access road construction
  • 68 Each timber piles
  • 415 CY concrete
Beard Contract Value: $ 3.96 Million
Project Start Date: April 2010
Completion Date: November 2010
 
 

 